How long does it take to build an app? A realistic timeline
Three to six months from kick-off to both app stores for a first version, as of October 2026. Each phase, what delays apps, and how to go faster.
By Sohail Hussain21 November 20265 min read
A first version of a business app takes three to six months from kick-off to live in both the App Store and Google Play, as of October 2026. A simple app with accounts, a handful of screens and a straightforward backend takes ten to fourteen weeks. An app with payments, notifications, maps and an admin panel takes four to six months. Apps with real-time features, offline sync or several integrations take six months or more. The screens are rarely what sets the pace; the backend, the integrations and the speed of decisions are.
How long does each phase take?
| Phase | Typical length | What happens |
|---|---|---|
| Discovery and scope | 1 to 3 weeks | Brief, core flows, feature list split into launch and later, estimate |
| Design | 4 to 6 weeks | User flows, every screen for both platforms, a clickable prototype, approval |
| Build | 8 to 16 weeks | App, backend and admin panel in parallel, with a test build every week or two |
| Testing and beta | 2 to 4 weeks | Your team uses real builds through TestFlight and Google Play testing tracks |
| Store review and launch | 1 to 2 weeks | Listings, submission, usually at least one rejection to fix, release |
Phases overlap. Backend work starts while the last screens are being designed, and beta testing begins before the final features are finished, which is why the total is shorter than the sum of the columns.
In hours, a medium app with accounts, payments, push, a backend and an admin panel is usually 800 to 1,800 hours of work, as covered in how much a mobile app costs. A small team of a designer, two developers and part of a project manager's week gets through that in roughly three to five months.
Our mobile app development projects follow this sequence, with a build on your own phone every week or two from the middle of the build phase so there are no surprises at the end.
How long do simple, mid and complex apps take?
| Type | Example | Kick-off to both stores |
|---|---|---|
| Simple | Accounts, five to ten screens, one user type, a straightforward backend | 10 to 14 weeks |
| Mid | Payments or subscriptions, push, maps or camera, two user types, an admin panel | 4 to 6 months |
| Complex | Real-time features, offline sync, integrations with existing systems, several roles | 6 months and up |
Two features move an app up a row on their own. Offline sync adds 100 to 250 hours because every screen needs a plan for what happens without a connection and when two people change the same record; offline-first apps explains why. In-app purchases and subscriptions add 60 to 120 hours, much of it testing purchase, renewal, cancellation and restore flows on both stores.
What makes app projects run late?
Decisions. Every screen needs approving, every flow has edge cases someone must rule on. A project with one decision-maker who replies within two working days runs to plan. A committee that meets weekly adds weeks.
The backend and integrations. Connecting to an existing ERP, CRM or booking system is where estimates go wrong, because the other system's API is often undocumented, slow or missing what you need. Ask for access and documentation in week one.
Store accounts. Apple's organisation enrolment needs a D-U-N-S number and a verification check, and the Apple Developer Program can take days to a few weeks to approve a new company. Google Play requires new personal developer accounts to run a closed test with at least 12 testers for 14 continuous days before an app can go to production, according to Google's testing requirements. An organisation account avoids that test, but has its own verification. Open both accounts in your company's name in the first week of the project.
Store review. Apple says it reviews at least half of submissions within 24 hours and 90 percent within 48, on its App Review page. The delay is rejections: a missing demo account, a privacy declaration that does not match the app, or a payment flow that breaks the rules. Budget a week, and read App Store rejection reasons before you submit.
Content. Product data, help text, legal pages, store screenshots and descriptions. They are always someone's job and always late.
Scope that grows. "While we're at it" is the most expensive phrase in app development. Write new ideas on a list for version two.
Can you build an app faster?
Yes, by cutting work, not by adding people. More developers on a small app add coordination, not speed.
- Cut the first version to one core flow. The thing your users must do, working well, on both stores. Everything else waits for evidence it is needed.
- Use an existing backend. If your website or system already has an API, the app becomes a client of it and the build shrinks substantially.
- Launch one platform first. If your users are overwhelmingly on Android or on iPhone, ship there and add the other a few weeks later. With a cross-platform codebase the second platform is a fraction of the first.
- Decide fast. Name one approver and agree a reply time.
Some things are not worth rushing. Skipping the beta to hit a date usually means launching with bugs your own team would have found, and the first store reviews are written by the people who hit them.
Our project timeline calculator lays out the phases against a launch date, and the app cost calculator shows how each feature affects the budget, which moves in step with the timeline.
What happens after launch?
The first four to six weeks are for fixes and small changes based on how real users behave. After that, apps settle into a cycle of updates: Apple releases a new iOS each September, Google releases Android versions and raises its target API requirement each year, and libraries move on. Each needs testing and often changes. App maintenance: what it involves and costs covers the yearly calendar and the budget, typically 15 to 25 percent of the build cost a year.
If you are still planning, a written mobile app brief is the fastest way to get a timeline you can trust, because every developer quotes the same app. The mobile app development guide covers the rest of the decisions in order.