How long does it take to build a website? Realistic timelines
A 5 to 10 page company website takes 4 to 8 weeks when the content is ready and 10 to 16 when it is not. Where the weeks go, and how to shorten them.
By Sohail Hussain29 October 20265 min read
A company website of five to ten pages takes four to eight weeks to design and build with an agency, if the content is ready when the project starts. If the content is not ready, expect ten to sixteen weeks, because writing is the step everything else waits on. A template site on a builder can be live in a weekend. An online store takes two to four months; a custom web app, three to six or more. These are typical agency ranges as of October 2026; the rest of this post explains what moves a project to one end of the range or the other.
How long does each type of website take?
| Type of site | Typical time | What drives it |
|---|---|---|
| One-page or template site on a builder | 1 day to 2 weeks | How fast you write the copy |
| Company website, 5 to 10 pages, custom design | 4 to 8 weeks | Content readiness, rounds of feedback |
| Company website, 15 to 30 pages, with a CMS | 8 to 14 weeks | Content volume, number of page templates |
| Redesign and migration of an existing site | 6 to 12 weeks | Redirects, content clean-up, number of old URLs |
| Online store | 8 to 16 weeks | Product data, payments, shipping rules |
| Multilingual site (for example English and Arabic) | Add 2 to 4 weeks | Translation, right-to-left layout |
| Custom web app or portal | 3 to 6 months and up | Scope, integrations, testing |
The build itself is rarely the long part. On a typical company site, development is two to three weeks. The rest is deciding, writing and approving.
Where do the weeks go?
A website design and development project at our studio runs through six phases. The durations below assume one decision-maker who replies within two working days; more approvers or slower replies stretch every phase.
| Phase | What happens | Time |
|---|---|---|
| Discovery and sitemap | Goals, visitors, page list, URLs, platform | 1 week |
| Content | Copy, photos, logos and testimonials gathered | 1 to 4 weeks, overlapping the next phase if ready |
| Design | Homepage and one inner page first, then the rest | 2 to 3 weeks |
| Build | Templates, CMS, forms, integrations | 2 to 3 weeks |
| Review and fixes | Your review on real devices, copy tweaks, browser testing | 1 week |
| Launch | DNS, redirects, analytics, Search Console, checklist | 2 to 3 days |
Added up, the arithmetic says seven to twelve weeks. In practice the phases overlap: design starts while content is finished, build starts on approved pages while others are still in design. That overlap is how a well-run project lands at six to eight. Our project timeline estimator lets you set the phases and the team size and see the result with a buffer for dependencies.
Why do website projects run late?
Four causes account for almost every late website we have seen, including our own.
Content arrives late. The agency cannot design a page around text that does not exist. Placeholder text leads to layouts the real copy does not fit, which leads to a second design round. Write first, or hire a copywriter at the start; our guide to website copywriting explains what each page needs.
Feedback is slow or crowded. One round of feedback that takes a week, from five people with different views, costs more time than the design itself. Name one decision-maker. Collect feedback in one document, not five email threads.
Scope grows. "While we are at it, can we add a careers section and a Hindi version?" Each addition is reasonable; together they double the project. Keep a list of post-launch additions and ship the core first.
Third parties. Domain access held by a former employee. A CRM that needs an API key from a vendor who takes two weeks. Photography scheduled for after the design review. List every external dependency in week one and chase it from day one.
Can a website be built in a week?
Yes, under narrow conditions: a small site, a template or an existing design system, the content already written, and one person approving. Agencies and freelancers do this for landing pages and one-page sites. Our own company website work does not usually fit that shape, because the discovery and content phases are where most of the value is, and they are the phases a one-week build skips.
Be wary of the opposite promise too. A fixed-price "website in 30 days" package can be a good deal if it is honest about what is excluded. Ask what happens to the deadline when your content is late, and whether revisions are capped.
How do you shorten the timeline without cutting corners?
- Finish the content before the kick-off. This alone moves a project from the slow end of the range to the fast end.
- Approve the homepage design and one inner page, then let the rest follow the pattern. Reviewing every page as a separate design round is what makes design phases run to six weeks.
- Decide the platform and the domain before the project starts. Both are covered in our website planning guide.
- Batch feedback. One document, one round per phase, one person with the final word.
- Launch with the core pages and add the rest after. A site with eight finished pages beats one with twenty unfinished ones. The launch checklist covers what must be in place on day one.
When is a slower build the right choice?
If the site is replacing one with years of search traffic, take the extra two weeks to map redirects and clean up content. A fast migration that drops rankings costs more than the time it saved. If the brand itself is being redone, finish the brand first; designing a site around a logo that will change is wasted work. And if you cannot write the content in the next month, delay the kick-off rather than paying an agency to wait.
What happens after launch, and how long does that take?
Launch day is not the day the site starts working for you. Google has to crawl and index the new pages; its documentation says this can take from a few days to a few weeks. Rankings for new pages settle over the following months. Plan the first ninety days as part of the project: watch Search Console, test the forms monthly, fix what the analytics show. Our post on what to do after launch has the schedule.
For what these timelines cost, see how much a website costs. Time and price move together, and the fastest way to control both is the same: have the content ready before the clock starts.